The Malé North Side Boduthakurufaanu Road Development Project Phase 2 has reached 82% completion, the Maldives Transport and Contracting Company (MTCC) reported.

Reclamation, sheet piling, panel installation, dewatering, stormwater catchpits, cable junctions, and water and wastewater pipe laying have been completed. Quay wall capping final concrete is scheduled to finish today.

Work continues on curb stones, settlement tanks, and trench concrete. Road sub-base preparation and asphalt works are set to begin this week.