Preparations for the reclamation phase of the Malé North Side Boduthakurufaanu Road Development Project are progressing smoothly, with anchor block installation underway for Phase 2.
Work on the road’s infrastructure is advancing steadily. Curbstone installation on the building side of the road has reached 85% completion and is expected to be finished by the end of this week. In parallel, new wastewater and water line installations are 45% complete, and cable junction works have already commenced.
The project aims to transform Malé City’s infrastructure by creating modern, pedestrian-friendly roads, improving accessibility, and enhancing urban mobility for residents and visitors alike.