MTCC has completed sheet piling works for the second phase of the Boduthakurufaanu Magu redevelopment project.
MTCC said it has finished installing 85 metres of sheet piling under the project’s second phase. The company added that land reclamation work, along with upgrades to the water and wastewater networks, will be completed by the end of next week.
The project also includes the installation of sidewalks, stormwater catch pits, and cable junctions. MTCC said these works are progressing as planned.
The second phase of the project covers the stretch from the local market to North Harbor. MTCC said it aims to complete the full development by Ramadan next year.