Reach out on facebook
Follow us on instagram
Get the latest updates
Discover Our TikTok
Stakeholders Discuss Hanimaadhoo Airport Opening
Stakeholders Discuss Hanimaadhoo Airport Opening
Land Reclamation Project in Hirilandhoo Reaches 78%
Cabinet Approves Referendum on Addu Council Restructuring
Cabinet Approves Referendum on Addu Council Restructuring

Land Reclamation Project in Hirilandhoo Reaches 78%

Land Reclamation Project in Th. Hirilandhoo Reaches 77%
Land Reclamation Project in Th. Hirilandhoo Reaches 77%

Land reclamation and shore protection in Th. Hirilandhoo have reached 78% completion.

MTCC is carrying out the project for the Ministry of National Planning and Infrastructure. The contract was signed on November 10, 2020. Site mobilization began on May 23, 2022, with physical work starting soon after.

Crews now carry out revetment work on site. The $105.9 million project covers 25 hectares of reclamation. It also includes 1,080 meters of revetment and 80 meters of groyne construction.

MTCC said the project will expand land for development. The company added that it will also strengthen coastal resilience and support the island’s future growth.