The Hulhumalé Phase 3 land reclamation project has reached 98 percent completion, with 62 hectares reclaimed so far.
Maldives Airports Company Limited (MACL) said reclamation works are progressing steadily under Phase 3, which aims to reclaim a total of 63 hectares of land.
The work is being carried out using two dredgers Prins der Nederlanden and Oranje each with a capacity of 22,000 cubic meters.
MACL said Phase 3 reclamation works resumed on November 10, 2025, and the project is now nearing full completion.